The fire alarm system at Baltimore’s Central Booking and Intake Center is “failing regularly,” causing dangerous conditions, and state officials are moving to replace it.

Under an “emergency” contract, Maryland’s Board of Public Works is set Wednesday to consider awarding $63,000 to Koffel Associates Inc. of Columbia for engineering and architecture work on a new system.

Advertisement

“The 23-year-old fire alarm system at the Baltimore City Booking and Intake Center failed regularly …. and was inadequate to protect the facility, the workers, and the 954 detainees,” the board’s agenda states. “Repeated efforts were made to repair the system with results that did not last.”

In October, the board awarded a $1.2 million contract to Star Electric Co. Inc. of Odenton to provide and install the new system.

49-year-old man dies at Baltimore Central Booking, minutes after he called two relatives

Another detainee died at the Baltimore Central Booking and Intake Center facility Thursday night, just minutes after he called relatives. The death caused the facility to be shut down while authorities investigate, according to the Maryland Department of Public Safety and Correctional Services.

According to board documents, an “emergency” contract was deemed necessary in July.

Central Booking is the state-run jail where detainees are typically brought after being arrested by Baltimore police.

The three-member Board of Public Works, which oversees significant state expenditures, is composed of Gov. Larry Hogan, a Republican, and Comptroller Peter Franchot and Treasurer Nancy Kopp, both Democrats.