Bid to join sewage spill talks denied

Blue Water Baltimore's David Flores samples Gwynns Run for sewage ocntamination just downstream from a large storm-drain outfall. (Amy Davis, 2011)

A federal judge has denied - for now, at least - Blue Water Baltimore's bid to intervene in the city's effort to delay its court-decreed deadline for fixing the pervasive sewage leaks that foul local streams and Baltimore's harbor.

In a brief five-sentence ruling filed earlier this month, U.S. District Judge J. Frederick Motz declared "untimely" the environmental group's motion to participate in talks between city officials and federal and state regulators over the 2002 consent decree requiring Baltimore to fix its largest sewage overflows.  The city  has estimated it would spend $1 billion upgrading the sewer system by the deadline, 2016.

Advertisement

Those talks to extend that timeline apparently began three years ago.  That's when, according to letters released earlier this year, the city wrote the Environmental Protection Agency and Maryland Department of the Environment asking for a 3 1/2-year delay in the deadline.  City public works officials said they needed more time to complete studies and coordinate with Baltimore County, where the Gwynns Falls and Jones Falls begin their journey to the harbor.

The talks only became public knowledge this summer, though. Blue Water Baltimore, which campaigns to restore the region's streams and harbor, filed a motion in August seeking a place at the table, arguing that the city is violating the terms of the consent decree and neither state or federal regulators were adequately enforcing it.

Advertisement

The city reported discharging more than 7 million gallons of raw sewage into Baltimore's streams and harbor from 2010 through 2012, the group said, while raising questions about how complete those reports were.  The group also argued there was evidence the city was not promptly posting streamside signs alerting the public to sewage overflows and cleaning up any spilled wasted debris, as required by the decree.

Lawyers for the city, EPA and MDE opposed the group's involvement, arguing among other things that its petition was premature since no changes had been proposed so far to the agreement approved by the court 11 years ago.

Motz adid not address the group's allegations about violations, writing instead that if and when any changes are formally submitted to the court, "Blue Water will be given an opportunity to express its views concerning the proposed modifications."

Halle Van der Gaag, Blue Water Baltimore's executive director, said the group was disappointed by the judge's decision, but hopeful it would be allowed to participate when changes to the agreement are submitted to the court.

Advertisement

"Regardless of the court's decision, we hope that the City will increase activities needed to address these issues," she said in a prepared statement, including better spill notification, faster cleanup and stopping raw sewage from leaking into streams via storm drains.

"We also believe better reporting and accountability is essential for public confidence in their government," she added. "Independent labs and Baltimore City's own data show the streams and Harbor are highly contaminated with sewage, and increased corrective action from the City and oversight by regulators is still very much needed."

Advertisement

Jeff Raymond, a spokesman for the city's

Advertisement
Advertisement
YOU'VE REACHED YOUR FREE ARTICLE LIMIT

Don't miss our 4th of July sale!
Save big on local news.

SALE ENDS SOON

Unlimited Digital Access

$1 FOR 12 WEEKS

No commitment, cancel anytime

See what's included

Access includes: