The planned closure of a section of Moores Mill Road scheduled to start last month has been delayed until the spring, county officials said.
The planned closure of a section of Moores Mill Road scheduled to start last month has been delayed until the spring, county officials said. (David Anderson/Aegis file)

The planned closure of a section of Moores Mill Road, scheduled to start last month, has been delayed until the spring, county officials said.

Moores Mill between Hickory Avenue and Rock Spring Road was to close Nov. 26 for two months of construction, then be re-opened and closed again in the spring to complete the project, according to Cindy Mumby, a Harford County spokesperson.

Advertisement

A utility issue created the delay, she said.

When the contractor was installing a new storm drain line, he found a water service connection on Chesney Lane. The connection, Mumby said, is owned by Maryland American Water Company, which provides water to Bel Air.

Harford approves $2.5 million contract for next phase of Moores Mill Road rehab and repaving

Harford County government is getting ready to rehabilitate, widen and repave the stretch of Moores Mill Road on Bel Air’s north side between Route 1/Hickory Avenue and Route 924/Rock Spring Road.

“The connection would have to be relocated with the storm drain,” Mumby said. “But then the road would be torn up during the holidays, disruptive for residents and travelers.”

The rest of the work is dependent on the weather and temperatures, she said.

“So in the best interests of all concerned, we decided to delay the closure until the spring,” Mumby said.

The spring closure will complete the project, which the county estimates will start in mid-March and end sometime in July, she said. The delay will not add significantly to the spring closure.

“We will announce the closure when we have dates well in advance so folks can plan ahead,” Mumby said.

The $2.5 million project, awarded to Allan Myers of Fallston, includes widening and resurfacing the heavily traveled road on the north side of Bel Air. The contract also covers utility relocation, some of which are in progress, and the eventual installation of sidewalks.

The county also plans to install a pedestrian crossing in the vicinity of Ma & Pa Road, south of Bel Air Memorial Gardens, as part of the future Ma & Pa Trail extension between Williams Street and Blake’s Venture Park.